• Capabilities: Engineering

MTR Whampoa station and overrun tunnel, HKSAR

Hong Kong - Arcadis was responsible for the detailed design of a new MTR underground station and over-run tunnel to be constructed as part of the Kwun Tong Line Extension.

 Connecting commuters in densely developed urban area

It was built 25 metres beneath the busy streets of Hong Kong’s second largest private housing estate. The station design has a single platform, two concourse areas and a 100m long  connecting platform tunnel.

CHALLENGE

The challenge would be to minimise street-level construction impact as the station is located within rock and mixed ground conditions located close to residential tower blocks and major utilities. Arcadis’s work also included re-configuration of an existing footbridge across Hung Hom Road and the design of major utility and traffic diversions.

SOLUTION

Our partnering approach enabled rapid design decisions during the extremely tight design program and public consultations and workshops helped garner community support during the design process. The traffic deck system kept everything running smoothly throughout the construction works. The original scheme was streamlined minimizing construction waste, construction work on site and reducing the overall footprint of the station.

 KEY OUTCOMES

  • The HKIE Structural Division Structural Excellence Award 2018 – Project Award -  Commendation Merit Award
  • Improving mobility for 50,000 Whampoa residents from 10,000 households

Questions about this project

Rupert Leung

Head of Engineering Solutions, Asia +852 2911 2000 Ask me a question
Share on Wechat
"Scan QR Code" on WeChat and click ··· to share.