For a decade, the industry met rising energy demand with better efficiency. With the increased rack densities associated with AI and high-performance computing (HPC), however, efficiency alone cannot meet the rising energy demand, and the constraint has moved from the building to the grid.

 

With expert insight from Jeff Gyzen, Global Practice Group Director, Mission Critical, Arcadis

 

Executive summary

The rapid growth of AI data centers is driving unprecedented increases in data center energy consumption, power demand, and cooling requirements. While energy efficiency improvements and liquid cooling technologies can reduce the energy required to support higher-density AI workloads, they do not eliminate the industry's primary challenge: securing enough power to support continued growth. As rack densities rise from tens to hundreds of kilowatts per cabinet, grid availability, power procurement, cooling strategy, data center water usage, and long-term infrastructure planning have become critical business decisions. For developers, operators, and investors, the key question is no longer how efficiently a facility uses power, but whether sufficient power and cooling capacity can be delivered when and where they are needed.

 

 

An operator sets out to convert an existing data center for AI. Everything seems promising: the building is sound, the fiber is in, and the power is already contracted at 50 megawatts (MW), contracted with the utility years ago and paid for ever since. On paper, it is the cheapest AI capacity anyone will find this year.

However, when you look closely at the density math, it’s not quite the bargain it seems. That 50 MW is spread across 1,000 racks of existing cloud-era equipment, each drawing 50 kilowatts (kW), but a single AI rack can draw the full 500 kilowatts on its own. The conversion concentrates the capacity already there into 100 cabinets, and the other 900 racks come out. The conversion does not add capacity to the room because the power entering the building never changes.

That calculation is where many conversations about AI data center energy demand and AI data center power consumption now end, and it explains why the industry’s habitual answer to rising demand is no longer sufficient. Energy efficiency was the right response when the primary constraint was operating cost. Today, the binding constraint is supply: efficiency can increase the compute delivered by a fixed power allocation, but it cannot create additional grid capacity.

“We are currently designing data centers with cabinet densities of 600 kW, and current trends will soon see as much as 1.2 MW per cabinet. The footprints stay the same. It’s the rack densities that increase,” says Jeff Gyzen, Global Practice Group Director, Mission Critical at Arcadis.

This shift did not arrive gradually. Rack density is the variable that moved, and a decade of design assumptions built around it—racks at eight to 12 kilowatts, air cooling, a utility connection you could count on—gave way at around the same moment. What replaced them isn’t a bigger version of the old problem, but an entirely new engineering challenge.

Behind those megawatts sits something easy to lose sight of: this demand comes from people. Someone waiting on a translation, a diagnosis, a search result—all of it is expected instantly. The facilities serving that demand are built in specific places, alongside communities that experience their noise and pressure on local infrastructure. The actual brief is to meet digital demand without transferring an unacceptable burden to the places that host it.

 

For the people financing these data centers, this shift has a sharp edge: the efficiency case and the power procurement case are now the same case, and both must be settled before design begins in earnest.

White paper
Turning power constraints into opportunity
Power availability is reshaping how data centers are planned, delivered and scaled. Discover how battery energy storage and smarter energy strategies can help organisations unlock capacity, improve resilience and create greater flexibility for future growth.

Why the grid, not the building, sets the limit on AI data center power consumption

The first consequence of higher density is obvious: higher power consumption. The second consequence is easier to miss: power becomes heat, the heat becomes cooling load, and the cooling load draws power again. Density never lands in one place but compounds through the whole system.

But the constraint that stops projects sits outside the fence line.

 

What clients most often misunderstand is that public utilities operate on a very different timeline. In Tier 1 markets, most of them can’t deliver additional capacity for three to 10 years.

Jeff Gyzen, Global Practice Group Director, Mission Critical

 

Tier 1 markets are the established hubs where most capacity has been built, and where the queue is longest. If a utility cannot serve a site within the project’s viable development window, the project must secure an alternative power route, relocate, or stop. That is why developers and hyperscalers—the largest cloud operators—increasingly treat on-site generation as part of the baseline power strategy rather than as a contingency.

Two workers in safety gear walking through an electrical substation.

It also means the energy conversation can no longer start at design. It now starts at the property search.

“When we search for property, we’re looking for available power first. If none is found, we look at the potential for natural gas, which we can use to generate our own,” says Jeff.

Leave that question late and you don’t end up with a worse design. You end up with a project that can’t procure the power at all.

Where AI data center energy consumption goes

Power Usage Effectiveness (PUE) is the ratio of a data center’s total energy use to the energy used by its IT equipment alone. As AI data center power consumption increases, operators are paying closer attention to both energy efficiency and the cooling systems responsible for managing the resulting heat load. A PUE of 1.0 would mean every watt reaches compute. PUE can be categorized into three types associated with design and actual operation. Design PUE models expected efficiency from planned equipment loads and design conditions before the data center is constructed and starts running. Daily PUE tracks efficiency over a 24-hour cycle to capture day-to-night temperature swings. Annual PUE measures full-year performance to smooth out seasonal weather shifts. Typically, data centers are designed to a higher Design PUE of 1.3 or more to accommodate worst-case scenarios over the life of the asset. Actual Daily and Annual PUEs can be much less in more energy-efficient designs, where PUEs can approach 1.1 or below.

Inside the building, most of the data center energy consumption reaches the servers. The remainder splits between cooling those servers and what Jeff calls housekeeping: lighting, controls, and everything else that keeps the facility running. In AI data centers, cooling can account for a significant share of total facility energy consumption, making liquid cooling and heat-rejection strategies increasingly important to overall performance.

That ratio is about to move sharply. NVIDIA is pushing the industry toward 45°C cooling water temperatures, and warmer water is cheaper to produce: less mechanical refrigeration, more hours of free cooling.

“With the changes NVIDIA is pushing the industry to implement, PUE will drop dramatically,” says Jeff. 

Why PUE is no longer the only measure of data center energy efficiency

PUE remains the industry’s default measure of data center efficiency. It is useful. It is also soft in ways that tend to favor whoever is quoting it.

“PUE has problems,” says Jeff. “It can be manipulated to get lower numbers.”

The manipulation is rarely dishonest; it is usually selective framing. Design PUE is typically modeled at full rated IT load with weather and operating assumptions that vary by methodology. Annual PUE divides a full year of facility energy by a full year of IT energy, capturing every seasonal swing and every hour of summer cooling. Average PUE is based on whatever measurement window someone chooses: an hour, a day, or a month.

The gaps are wide enough to change a decision. Annual PUE will sit below a peak-summer snapshot and above a winter one. Because real facilities rarely run at full load—and efficiency falls away sharply at partial load—the figure in a marketing deck often describes a building that does not exist yet under conditions it will seldom experience. Water Usage Effectiveness (WUE), a common measure of data center water usage that divides annual water consumption in liters by IT equipment energy use in kilowatt-hours (kWh), has a parallel problem and a larger blind spot.

“WUE typically misses indirect off-site water consumption—the massive volume used by utility plants to generate the electricity the data center consumes. It also fails to account for regional water scarcity, and it doesn’t distinguish between potable water and recycled wastewater,” says Jeff.

Two facilities can post an identical WUE while one draws drinking water from a stressed aquifer and the other runs on reclaimed municipal effluent.

So, what should leadership track instead? Start with total power draw and overall data center energy consumption, because together they determine whether a site is viable, what it costs to run, and whether the grid can serve it. But do not treat these measures as a complete sustainability picture. Total power draw says nothing about the energy source, water impact, or local environmental burden. The practical answer is a small, clearly defined set of measures: total power draw for commercial viability, annual PUE for operational efficiency, and a context-adjusted view of water and emissions for environmental impact.

 

Energy efficiency is no longer the primary constraint on AI data center growth. As AI workloads drive unprecedented power density and energy consumption, the determining factor is whether enough power can be secured and delivered when it is needed.

 

Designing AI data centers for density: Liquid cooling, heat and water

The liquid cooling options that replace air cooling at AI densities are more settled in practice than the industry marketing may suggest. Two of them do almost all the work.

Direct-to-chip liquid cooling handles around 80% of the load in many high-density rack configurations, with rear-door heat exchangers capable of serving much of the remainder up to a practical ceiling near 60 kilowatts. Racks at 300 kilowatts may combine the two approaches. Above that level, direct-to-chip cooling is likely to carry the dominant load, supplemented by liquid cooling for non-chip components.

Immersion cooling, for all the attention it attracts, has struggled in operation.

“Single-phase immersion tanks are filled with vegetable oil-based fluids or other synthetic options, so any board that needs work has to go to a dedicated cleaning station first. It’s messy, and maintenance staff prefer to avoid it.” says Jeff.

Two-phase immersion solves the mess—the fluid’s low boiling point means it evaporates as boards leave the tank, so they can be worked on immediately—but the fluids are not environmentally friendly.

The same physics govern retrofit decisions. Unless the utility upgrades the service, the facility’s total available power remains fixed. Increasing rack density therefore concentrates that power into fewer cabinets rather than increasing the building’s overall compute capacity.

Water has become as contested as power, though its effect on design is more specific than the coverage implies. The move to closed-loop air-cooled systems has been underway for over a decade, slowed by economics; evaporative cooling is more efficient and cheaper; therefore, hyperscalers have been slow to give that up. The advantage of closed-loop is simple: once charged, it needs no further water. Compared with evaporative cooling systems, closed-loop approaches can significantly reduce ongoing data center water usage, an increasingly important consideration in regions facing water constraints. However, they require more energy because they are less efficient at removing heat.

Aerial view of industrial cooling units surrounded by trees.

This has a consequence worth stating plainly because it cuts against the prevailing narrative. Closed-loop systems can materially reduce water dependency and broaden the range of viable sites, although power availability, climate, permitting, and heat-rejection performance still set limits. A closed-loop facility may also avoid drawing continuously on the same water supply as nearby households, often an important factor in whether a community supports or opposes a project. That distinction matters at scale: a large AI factory using evaporative cooling may be unable to secure enough alternative water, leaving some demand to be met from the same supply the surrounding community uses.

It’s worth noting that the overall water usage imposed by a data center using a closed-loop cooling system doesn’t necessarily mean less water is used overall. In some cases, an evaporative cooling system may end up using less water. That’s because water, by volume, can carry roughly 3,500 times as much heat as air for the same temperature change. Therefore, an evaporative cooling system is vastly more efficient than a closed-loop system. Better efficiency means less utility power required in a grid-connected scenario. Since all utilities use water in their power generation cooling systems, less power means less water usage. The actual water usage depends heavily on the type of power generation used by the utility. Natural gas uses less water than both nuclear and coal.

And the efficiency lever most operators still leave untouched? Raising chilled water temperatures—the same principle NVIDIA is now forcing through the supply chain.

White paper
Turning power constraints into opportunity
Power availability is reshaping how data centers are planned, delivered and scaled. Discover how battery energy storage and smarter energy strategies can help organisations unlock capacity, improve resilience and create greater flexibility for future growth.

Does efficiency reduce AI data center energy demand?

No. It accelerates it.

 

Efficiency means you get more tokens per watt out of the available power. The better your efficiencies, the more power you have available for your servers.

Jeff Gyzen, Global Practice Group Director, Mission Critical

 

That is the crux. More tokens per watt does not mean fewer watts. Efficiency in an AI data center releases capacity for more compute rather than back to the grid, and more compute is precisely what it is spent on. Nor is there relief on the demand side. AI workloads run around the clock and are getting denser, not more flexible, so there is little to shape or schedule. And overprovisioning, expensive as it looks, is not a planning failure.

“You do have stranded power in a typical data center. But you have to design for the worst-case scenario. You design for peak load, and that inherently leaves power stranded,” says Jeff.

This reframes why efficiency is worth pursuing at all—and it is not, in Jeff’s account, an environmental argument.

 

Efficiencies are argued on an OpEx basis. Better efficiency translates to lower cost. Sustainability is the one argued on environmental grounds.

 

The commercial case for sustainability, meanwhile, has less to do with investor sentiment than with permission to build. Public opposition and local moratoria can stop a project outright, and where power is already the binding constraint, a site that cannot be approved is worth nothing at all. Communities weighing a facility against their own power bills and water supply are making a reasonable judgment, and the projects that answer that question early are the ones that get built.

What this means for developers, operators, and investors

Three practical consequences follow.

 

While regulatory requirements vary between regions, the objective should not.

“Design the most efficient data center possible, with the least water consumption. That shouldn’t change across markets. It’s something designers need to be more cognizant of,” says Jeff.

How Arcadis approaches AI data center energy demand and energy efficiency

The decisions that determine a facility’s efficiency are made at initial concept, because by the time the design is developed, the power and water a project can secure have largely been fixed by its location. The Terra Data Center in San Jose offers a clear demonstration. The project has 99.5 megawatts of on-site generation from natural-gas solid oxide fuel cells, which produce virtually no nitrogen oxide (NOx) or sulfur oxide (SOx) emissions. They still emit carbon dioxide—natural gas is a hydrocarbon—but their efficiency can reduce CO2 emissions by 20% to 50% compared with conventional fossil-fuel combustion. Combined heat and power can lift overall efficiency to around 90%, while initial PUE projections approach 1.15. The timing argument is sharper still: Pacific Gas and Electric (PG&E) forecasts roughly 1.8 to 3 gigawatts of data center capacity coming online by 2030, with around 60% of it already committed  with signed interconnection agreements. The fuel-cell power is available now.

Which leads to the question clients almost never ask at the outset, yet should.

 

What does the future hold for energy demand? Because if they don’t ask that, and demand increases, their facility may be outdated before it’s operational.

Jeff Gyzen, Global Practice Group Director, Mission Critical

 

Densities went from 12 kW per rack to 600 kW in roughly the time it takes to design, permit, and build one facility. Specifying to today’s numbers means specifying to the past.

Energy efficiency does not create supply. It creates appetite. The question is no longer how well a facility uses power, but whether the power will arrive on time.

This makes the brief clearer than it looks. Design for the curve rather than the current point on it: cooling that can be uprated without rebuilding, headroom in the electrical spine, and a power strategy that does not depend on a queue nobody controls. That is a solvable problem, and solvable now; the facilities that treat it as one will still be doing useful work for the people who depend on them a decade after they open.

 

Talk to our data center team about building a power, cooling, and infrastructure strategy that can keep pace with accelerating AI demand.

Arcadis works across the AI data center ecosystem, collaborating with leading technology providers including NVIDIA and Schneider Electric to help clients understand the infrastructure implications of rapidly evolving AI workloads.

Connect with our team

 

Frequently asked questions

 

 

Disclaimer: The figures and performance ranges in this article reflect current project experience and published industry guidance. Actual outcomes vary by climate, load profile, equipment configuration, utility conditions, and the definitions used for measurement.